Vertical Formwork System Delivers Precision and Efficiency for 11-Storey Dandenong Apartment Development

Project Overview 

When construction began on a new 11-storey residential apartment complex in Dandenong, Victoria, the project team faced a critical challenge: how to efficiently construct the building’s vertical core elements—stairwells and lift shafts—while maintaining strict dimensional accuracy across all floors. These vertical structures form the backbone of any high-rise building, requiring absolute precision and consistency from ground level to the top floor. 

The developer selected Cassaform’s P300 Wall Formwork System to handle these demanding vertical applications. This decision would prove instrumental in keeping the project on schedule while delivering the quality standards essential for modern residential construction. 

The Challenge 

Stairwells and lift cores in multi-storey buildings present unique construction challenges. Unlike typical walls that vary from floor to floor, these vertical shafts must maintain exact alignment throughout the building’s entire height. Even minor deviations can create serious problems—misaligned lift cores can prevent proper equipment installation, while inconsistent stairwell dimensions can fail building code requirements. 

The Dandenong project required formwork that could: 

  • Maintain millimeter-perfect vertical alignment 
  • Handle the substantial structural loads of reinforced concrete walls 
  • Enable rapid assembly and dismantling to keep pace with the construction schedule 
  • Adapt to the confined spaces typical of stairwell and lift core construction 
  • Deliver consistent concrete surface quality throughout 

Traditional formwork approaches often struggle with these requirements, particularly the need for both precision and speed across multiple floor cycles. 

The Solution: P300 Modular Formwork System 

The project team implemented Cassaform’s P300 Wall Formwork System, specifically configured for the vertical core construction. The system’s modular design proved ideal for the repetitive nature of high-rise construction, where the same formwork configuration is used floor after floor. 

For the stairwell construction, the team utilized the P300’s 3.0m height panels as the primary forming elements, supplemented with 1.5m and 1.0m panels where partial heights were required. This configuration matched the building’s floor-to-floor heights while minimizing the number of panel joints, each joint represents a potential point of misalignment. 

The lift cores demanded even greater precision. Here, the team took advantage of the P300’s enhanced load capacity of 60kN/m² , ensuring the formwork could safely handle the substantial concrete pressures during placement. The system’s panel widths, ranging down to just 0.050m, allowed the team to accurately form the tight spaces and corners characteristic of lift shaft construction. 

Cassaform’s in-house engineering team provided detailed support throughout the project, developing custom configurations for service penetrations and ensuring the formwork design met all structural requirements. This technical backing proved valuable when addressing site-specific challenges that emerged during construction. 

Results and Benefits 

The P300 system delivered measurable results across multiple project dimensions. The straightforward assembly process minimized labor requirements and kept the project timeline on track. Crews became increasingly efficient with each floor cycle, as the modular system’s repetitive nature reduced setup complexity. 

Cost efficiency emerged as a significant benefit. The panels’ durability allowed them to be reused without degradation, eliminating the material waste typically associated with single-use formwork systems. Given that formwork can account for up to 50% of a project’s total concrete costs, this reusability translates into substantial savings. 

Quality outcomes exceeded expectations. The consistent formwork produced uniform concrete surfaces throughout the stairwells and lift cores, reducing the finishing work required and ensuring the lift equipment could be installed without dimensional complications. The vertical alignment remained within tolerance across all floors, a testament to both the P300 system’s design and the climbing system’s precision. 

Safety performance remained strong throughout the vertical construction phase. The system’s robust design, with load capacities of 60kN/m² for walls and 80kN/m² for columns, provided confidence that the formwork could safely support the concrete loads. Compliance with industry standards including ACI 347-04 ensured the installation met all regulatory requirements. 

Conclusion 

The Dandenong apartment project demonstrates how selecting the right formwork system can address the specific challenges of high-rise vertical construction. The P300’s combination of modular flexibility, structural capacity, and reusability proved well-suited to the demanding requirements of stairwell and lift core construction across floors. For developers and contractors facing similar multi-storey projects, the case illustrates the value of formwork systems engineered specifically for vertical applications where precision, efficiency, and safety are non-negotiable requirements. 