Slabprop Back Propping Design & Supply for a Multi-Level Suspended Slab

Slabprops

Backprop

This case study examines how Cassaform provided an engineered back propping solution for a 4-level suspended slab construction project, replacing conventional Acrow props with high-capacity Slabprops to optimise construction efficiency, reduce costs, and maintain safety standards. 

Client Challenge

The client faced several challenges in their multi-level construction project: 

  • Required an effective back propping solution for a 4-level suspended slab project 
  • Needed to cycle formwork efficiently up the structure to minimise equipment requirements 
  • Wanted to reduce congestion on site to improve workflow 
  • Initially planned to use standard Acrow props for back propping 

Backprop

Cassaform’s Solution 

After analyzing the client’s requirements, Cassaform developed a comprehensive solution: 

  • Provided custom-engineered back propping designs specifically tailored to: 
    • The slab thickness specifications 
    • The client’s slab cycle requirements 
  • Recommended replacing conventional Acrow props with Cassaform’s high-capacity Slabprops 
    • Designed and manufactured in Italy with superior load-bearing capacity 
    • Comprehensive drawings 
    • Precise layout plans 
    • Guidelines to ensure compliance with safety standards 
    • Instructions for proper load transfer between levels 

Backprop design

Key Benefits Delivered

Improved Efficiency 

  • Reduced prop quantity by approximately one-third thanks to Slabprop’s superior load-bearing capacity 
  • Increased site productivity by enabling faster cycling of formwork to upper levels 

Cost Reduction 

  • Lowered labour costs due to fewer props needing installation and removal per level 
  • Reduced overall equipment hire requirements 

Enhanced Site Operations 

  • Reduced site clutter creating a more organized work environment 
  • Improved movement of materials and personnel between levels 
  • Simplified installation and removal processes 

Backprop delivery

Project Outcome 

The implementation of Cassaform’s Slabprop solution delivered significant results: 

  • Project maintained slab cycle targets with fewer delays 
  • The client achieved savings on both labour and hire costs while maintaining high safety standards 
  • Site team provided positive feedback regarding: 
    • Ease of use of the Slabprop system 
    • Clarity of the layout documentation 
    • Overall improvement in construction workflow 

Conclusion 

By replacing conventional props with Cassaform’s engineered Slabprop system, the client was able to optimize their multi-level suspended slab construction process. The solution not only reduced costs and improved efficiency but also maintained crucial safety standards throughout the project. 

by Cassaform