Bass Coast Junior Secondary College Expansion Project, San Remo – Case Study

Cassaform were engaged to supply a fast, modular and reliable formwork system to help form rebate at the Bass Coast Junior Secondary College expansion project in San Remo.



Overview of Job: Bass Coast Junior Secondary College expansion project in San Remo involved the construction of five low rise steel structures supported of reinforced concrete (RC) foundation.
Key Features: Given the site conditions the RC foundation slabs required deep rebated edge beams in some instances up to 1300mm high around the perimeter of the building. These where quickly formed one sided using Cassaform’s P300 system and propping to a temporary footing.
Product used: Cassaform’s P300 formwork system.
Cassaform’s involvement: Cassaform were engaged to supply a fast, modular and reliable formwork system to help form rebate.
Feedback from job or results following completion: The RC slab was recently completed to the client’s satisfaction.
Click here to learn more about our P300 Modular Formwork System.
Click here to read about our Temporary Engineering Services.
Click here to request a call from our friendly team.
Clik here to view more case studies.