Cassaform was engaged to design and supply our P300 foundation formwork systems to the Arrow Energy Project west of Dalby Southern Queensland.





Overview of Job: The new wells are key components of Arrow’s Surat Gas Project and will contribute to our contractual obligations to provide around 300TJ/d gas to the local area.
Key Features: The project required the formation of approx. 200. lm of Reinforced Concrete foundations up to 4.2m wide to the David Inlet Processing Facility.
Product used: Cassaform P300 walling panels and Engineering Design Services.
Cassaform’s involvement: Cassaform were engaged to design and supply formwork systems to aid with construction of the reinforced foundation structure.
Feedback from job or results following completion: The project was completed to the clients satisfaction and budget.
Click here to learn more about our P300 Modular Formwork System.
Click here to read about our Temporary Engineering Services.
Click here to request a call from our friendly team.
Click here to view more case studies.